Lincoln |
Code of Ordinances |
Title 18. ZONING |
Division XI. ADMINISTRATIVE PROCEDURES—FEES |
Chapter 18.99. PUBLIC FACILITIES FEE |
§ 18.99.040. Developer construction of facilities.
Whenever a developer is required, as a condition of approval of a development permit, to construct a public facility described in the resolution adopted pursuant to Section 18.99.020, which facility is determined by the city to have the impacts of that development, and when such construction is necessary to ensure efficient and timely construction of the facilities network, a reimbursement agreement with the developer and a credit against the fee which would otherwise be charged pursuant to this chapter on the development project, shall be offered. The reimbursement amount shall not include the cost for that portion of the improvement needed to mitigate the burdens created by the development.
(Ord. 517B §1(part), 1989)